The Delta Rhine Corridor West (DRC West) project concerns the construction of underground pipelines for the transport of hydrogen and CO2 between Rotterdam and Boxtel via Moerdijk. These pipelines are needed to help industry in the Netherlands become more sustainable.
The Delta Rhine Corridor West (DRC West) project concerns the construction of underground pipelines for the transport of hydrogen and CO2 between Rotterdam and Boxtel via Moerdijk. These pipelines are needed to help industry in the Netherlands become more sustainable.
Industry in the Netherlands is responsible for a large part of the national carbon emissions. To reduce these emissions industrial companies need a sustainable gas, like (green) hydrogen for example. Besides taking measures to cut CO2 emissions, CO2 is also being captured and stored so that these emissions do not end up in the atmosphere. This helps prevent further climate change.
The CO₂ pipeline is also being installed between Rotterdam (Maasvlakte industrial area) and Boxtel. And it also passes through Moerdijk, where it can connect to the Delta Schelde Co₂nnection CO2 transport pipeline that continues southward to the Belgian border.
It is expected that the pipelines for hydrogen and CO₂ will be installed in the DRC West section of the corridor between 2031 and 2032.
DRC East
DRC West will connect to DRC East. The DRC East project only concerns building a CO₂ pipeline between Boxtel and the German border near Venlo, which will also create a connection between the Netherlands and Germany. A separate project procedure for the DRC East project is meanwhile underway.
DRC West and DRC East are part of the Delta Rhine Corridor that is currently under development. This corridor, which will accommodate a cluster of pipelines and cables, is planned to run between Rotterdam and Moerdijk and from there to the Dutch province of Limburg and further into Germany.
Where will the pipelines be located?
We are still looking into exactly where the DRC pipelines will be located. What is clear, however, is that in the Netherlands the starting point is the ‘PEH’ corridor, the area the Dutch government has reserved for pipelines under its Programma Energiehoofdstructuur [Main Energy Structure Programme]. This corridor runs from the port area in Rotterdam to Moerdijk and from there to the province of Limburg. Moerdijk naar Limburg. To see where this corridor is located, check the Interests Map.
You can read more about the Main Energy Structure Programme on the website of the Dutch Government.
Participation: your views and input are important
The project procedure
Some land-use projects are not only big but also particularly important – of national importance in fact. This also applies to DRC West. To make these types of projects possible, decisions on land use must be made and permits need to be granted. A special procedure is used for this: the Project Procedure under the Dutch Environment and Planning Act. The aim of this procedure is to speed up decisions for large energy projects without compromising the due diligence of decision-making and opportunities for residents to express their opinions.
The first milestone: project procedure underway
On Friday 5 September 2025, the exploratory phase of DRC West began with the publication of the following documents:
Notification of Intention / Proposal for Participation: this document describes the plans
Participation Plan: this outlines how the local community will be engaged in the procedure for the development of DRC West
Memorandum on the scope and level of detail: this is the research plan for the environmental impact assessment to be prepared later. This plan outlines which environmental impacts will be assessed and how they will be conducted. This helps ensure that careful consideration can be given when deciding on the exact route of the corridor.
You can read more about the latest state of affairs regarding the project procedure on the website of the Dutch Government. This is also where you can find out what project procedure steps are required before the actual building work for the project can start.
Stay up to date and let us know your thoughts
If you’d like to stay in the know on all the developments concerning DRC West, sign up for the newsletter. We invite everyone to share their thoughts and ideas with us through the ‘Interests Map’. Through this online map, which shows the route of DRC West (the ‘pipeline corridor’), you can ask a question, make a comment and/or share any other message.
DRC West newsletter
This newsletter is for anyone interested in the developments around the Delta Rhine Corridor West and the steps in the project procedure. The DRC project is divided into two procedures, each independent of the other: DRC West and DRC East. You can also subscribe to the DRC East newsletter.
Many people will be affected by the construction of the new pipelines that will be transporting hydrogen and CO2 along the DRC West section of the pipeline corridor. The ‘Interests Map’ allows everyone to let us know how the DRC West affects their interests. We would like to know this so we can get in touch with those individuals. So please share your question, concern, point of attention, suggestion and/or idea through the map.
If you’d like to stay in the know on the commercial (national and international) developments concerning the hydrogen network and the CO2 networks in the DRC and the Delta Schelde Co₂nnection, you can sign up for the various newsletters on the Delta Rhine Corridor page.
Contact
For any queries, please write to drc@gasunie.nl or contact our project team:
Memorandum on the scope and level of detail adopted for Delta Rhine Corridor West
Date
The Memorandum on the scope and level of detail (NRD) for Delta Rhine Corridor West has been adopted. The memorandum sets out what will be assessed in the environmental impact assessment (EIA) and how these studies will be conducted. This marks an important step in the further development of the project.
The Delta Rhine Corridor will focus on the construction of pipelines for hydrogen and CO2. Minister Sophie Hermans of the Ministry of Climate and Green Growth announced this in a parliamentary letter on 5 December 2024. With the change in the scope of the Delta Rhine Corridor (DRC), there has also been a new division in the DRC for the project procedures: DRC West and DRC East. DRC West is the route for CO2 and hydrogen from the Maasvlakte to Boxtel. DRC East is the route for CO2 from Boxtel to the border crossing with Germany near Venlo. In order to build the pipelines in the Delta Rhine Corridor as soon as possible, the project procedure for DRC West will be started first.